An estimate
line item is not calculating the way I want it to!
Here is a checklist of possible problems in Estimate line
items, based on what is in the Cost Area field. This troubleshooting
guide works for all versions of Goldenseal estimating
software.
Assemblies and Cost Items
First, hit the Update Prices button. That will fill
in the latest unit costs. If that doesn't solve the problem,
double-click on the Item Total cell to
view the Assembly or Cost Item, then check the following:
- Check the Project Price field in the Assembly
or Cost Item. It should match the estimate, with 2 exceptions
listed below.
- Does the item use a labor or material multiplier?
If so, it will adjust the price, depending on a
dimension value. The Unit Cost comes from the Assembly,
but the Item Total includes labor or material multipliers.
- Does the Assembly include a fixed
cost? If so, the actual unit
cost will vary, depending on quantity (it will also
have a * next to the price).
Bids & Allowances
If a Bid doesn't appear in the list of
available bids, check the following:
- What's in the Category column? It will only show Bids with that category.
Erase it to show all bids.
- Did you just add the Bid? In that case,
open the Bid and hit the Enter key to save it.
Then the Estimate will "see" it.
- What is the status of the Bid? If Void or In Use, it won't
show up in the list. HINT-- in that case, you can
duplicate the Bid and then include the duplicate.
- Is the Bid already included in the Estimate? You can't add
it twice.
- Click the link if still using an early version
of Goldenseal estimating
software (before 3.0).
The same checklist applies to Allowances.
Purchase Orders & Work Orders
If a Purchase/Work
Order doesn't appear in the list
of available PO's, check the following:
- What's in the Category column? It will
only show Purchase/Work Orders with that category.
Erase it to show all items.
- Did you just add the PO? In that case,
open the PO window and hit the Enter key to save
it. Then the Estimate will "see" it.
- What is the status of the PO? If Void
or In Use, it won't show up in the list. HINT--
in that case, you can duplicate the Bid and then include the
duplicate.
- Does the PO have a Job filled in? Erase
it and save the record (Goldenseal won't show PO's
that are already assigned to a project).
Percentage Adjustments
Percent of Hard is a percentage of all hard costs (including
Assemblies, Cost Items, Bids, Allowances, and unlisted items.
Percent of Total is a percentage of the total cost
(including both hard and soft costs).
Percent of Labor is based on all labor line items,
plus the labor component of Assemblies.
Percent of Materials/Equipment/Subcontractors/Other
are calculated similarly to Percent of Labor. Click here to return to estimating
topics.