Scheduling Dates

Problem

import to MacProject II or MacProject Pro from MacNail construction scheduling software-- why is there 11/1/90 showing?

Diagnosis

sees 11/1/90 or some other 'old' date in the MacNail Construction Blank, MacNail Const Blank for Pro or some other import file.
Sees 11/1/90 or some other 'old' date in the setup box when first importing to MacProject Pro.

Solution

ignore it!

The import uses the old date as a 'placeholder' only. MacProject will calculate new dates after the import is done.