Jobsite Gas Heat Costs |
Construction ITEM DESCRIPTION A construction unit cost that covers winter project site heating using city gas or propane. This applies mainly to remodeling projects where there is an existing furnace, or for new work when you can install the heating system early on. Labor Costs None included. Material Costs 120 therms of gas per day. Suggested Quantity No suggested quantity. Enter the number of days that you expect will require heating. Source of Construction Pricing Based on a couple of winter construction projects done by Turtle Creek Construction in Ithaca NY. You may want to adjust the heating required if your climate is warmer or colder than upstate NY. Places Included Architect Starter File, Construction Starter File, Developer Starter File, Metric Starter File Comments For more about Goldenseal construction estimating software, click