Backhoe Fill Work Cost

Construction ITEM DESCRIPTION

Excavation unit cost for backfilling trenches or other excavation work using a backhoe or bucket loader.

Unit Size

One cubic yard of soil or other fill.

Labor and Equipment Costs

We figure 37 cubic yards of soil per hour of backhoe time, plus one unskilled laborer hour for every 27 cubic yards of fill work.

The cost will cover backfilling from stockpiles relatively close to the backfill site. We have an additional backfilling unit cost for more difficult conditions.

Material Costs

None.

Suggested Quantity

No suggestion. Enter an estimate of the volume of backfill required.

Source of Construction Pricing

This pricing is based on estimates from our job cost data from Turtle Creek Construction. Use it as a "rule of thumb" price for average conditions, and replace it with firm subcontractor quotes if they are available.

Places Included

Architect Starter File, Construction Starter File, Developer Starter File

Comments

Click here for more about Goldenseal construction estimating software.

For other excavation estimating costs, click here.