name-- In Goldenseal Estimating Software |
romex 14-3 w/ground
|
Construction
Category |
SubCategory |
Rough Electric |
Boxes & Wiring |
Construction ITEM DESCRIPTION |
Electrical estimating unit cost for installation
of 14-3 non-metallic sheathed electrical wiring (primarily for 3
way switches).
|
Unit Size |
One lineal foot of wiring, installed.
|
Labor
Costs |
We figure about a skilled electrician can install
about 70 lineal feet of 14-3 wiring per hour. Add additional labor
time for snaking wires through existing walls.
|
Material
Costs |
One lineal foot of 14-3 non-metallic sheathed
"romex" cable plus a staple every couple of feet.
|
hard
COnstruction Cost, Typical |
$0.32 per lineal foot
|
Suggested
Quantity |
No suggested quantity. Enter the length of wiring
required.
|
Source
of Construction Pricing |
Based on subcontractor crew timing from electrical
installations done by Turtle Creek Construction.
|
Places Included |
Architect Starter File, Construction
Starter File, Developer Starter File
|
Click here for more about Goldenseal construction estimating software.
Click here for other rough
electrical construction
costs.
 |
|