Assembly Components

Problem

Wrong component in a few Assemblies used for construction estimating under the General Conditions category-- Architectural Drawings, Engineering Drawings, Lawyer, Consultant Time.

Caught By

Turtlesoft testing.

Workaround

Change the components to use Subcontractor cost area, and Professional wage rate. To do so:

  1. Choose Assemblies from the Costs menu.
  2. Browse to Engineering Drawings (it's the 16th item in the Construction Starter File)
  3. Click in the first component line, and enter Subcontractor into the Cost Area cell.
  4. Click in the Category cell and erase the category.
  5. Click in the Cost Item cell and enter Professional Wage.
  6. Repeat steps 1 to 5 for the next 3 assemblies (architectural drawings, consultant time, lawyer).

NOTE-- The 3.01 update for Goldenseal construction estimating software will not fix this problem automatically, since it is in the cost data rather than the program.