Showing Labor Hours

Problem

how, on a 2-layer cc, to get the labor hours showing in the summation as well as the subcat section for job costing worksheets in MacNail construction accounting software. Right now it only posts hours for each subcat and doesn't do a total, which is odd.

Diagnosis

if you paste into that column the SUM formulas from any cost row in the title row of each subcategory, plus the formulas in the 'summation' part at the top, it'll do that.

Solution

I'll make a note to have the code add those formulas in the next vsn, since several users have requested that we keep labor hours. The original intent was to use it for 'feedback job costs'-- we decided not to use it for that, but users like to see hours anyhow.

Comments

Entered 2/23/94 by Vinay. Updated 11/20/2010.