2x12 Floor Joists, 16" Spacing |
Construction ITEM DESCRIPTION Construction estimating unit cost for 2x12 floor joists framed at 16 " on center spacing. Unit Size One square foot of floor framing area. Labor Costs We figure about 39 square feet of framing completed per hour for a skilled carpenter with an unskilled helper. Material Costs We figure 1.08 lineal feet of 2x12 lumber per square foot (about 40% more than the theoretical coverage to allow for band joists, an extra joist at the end, doubled joists under bearing walls, etc). Suggested Quantity Upstairs floor area. Source of Construction Pricing Crew timing and material job costing from several construction projects done by Turtle Creek Construction. Places Included Architect Starter File, Construction Starter File, Developer Starter File, Framing Starter File. Comments Click here for more about Goldenseal construction estimating software. Click here for other framing estimating costs. |