PROBLEM

After changing the Working Hours, the schedule in an Estimate does not recalculate.

Caught By

User bug report.

Workaround

Move to a different record, come back, and click the Update Schedule button.

Solution

Starting with Goldenseal project scheduling software version 4.1, changing the Working Hours will change the schedule.

NOTE: If you are using manual schedule updating, you'll need to click the Update Schedule button to get a new schedule (set the schedule updating method in Options--Preferences--Income).

Technical Details

Programmer note-- code change in CEstimateViewer::DoScheduleUpdate