Schedule Updating |
|||||
PROBLEMAfter changing the Working Hours, the schedule in an Estimate does not recalculate. Caught ByUser bug report. WorkaroundMove to a different record, come back, and click the Update Schedule button. SolutionStarting with Goldenseal project scheduling software version 4.1, changing the Working Hours will change the schedule. NOTE: If you are using manual schedule updating, you'll need to click the Update Schedule button to get a new schedule (set the schedule updating method in Options--Preferences--Income). Technical DetailsProgrammer note-- code change in CEstimateViewer::DoScheduleUpdate |