Change Order Contract Specs |
|||||
PROBLEMMaking a contract for a change order picks up "scope of work" specifications from the main project, not the change order. Caught ByUser bug report in Goldenseal project management software. WorkaroundNone. SolutionFixed in version 3.5 Technical DetailsA change last summer accidentally zapped the ability to get a separate scope of work for allowances and change orders. |