Change Orders- Job Costing

PROBLEM

change orders posting won't work in MacNail construction accounting software
how to post and data enter change orders in MacNail construction job costing software
how to add change orders

Diagnosis

To data enter change orders:
In ledgers or logs, change orders must be entered with category code CO, and MUST have a subcategory, whether or not they are using a 2-layer cost control. The subcat # is the # of the change order- they can check the bottom of the cost control sheet to see which change orders are available.

Solution

To add change orders:
1. Make sure they're in the Cost Control Manager.
2. Scroll down to the very bottom of the worksheet, below the 'profit' section. They should see CO--Change Orders, with numbers beneath it.
3. Click anywhere in the row underneath the last change order--it'll be labeled AL-- ALLOWANCES.
4. Drag down thru any cells, selecting as many rows as you want to add.
5. Choose Add Rows from the Edit menu. # series is added automatically.