Construction Estimating Software
Construction Software
Estimating Software
Construction Estimation SoftwareConstruction Estimate SoftwareConstruction Estimates SoftwareConstruction Estimator SoftwareConstruction Bidding SoftwareConstruction SoftwareProject Estimating Software

Zeros in Summation

Problem

Valid numbers in specs headings, but zeroes in summation/clearinghouse portion of MacNail construction estimating software

Diagnosis

1. check overall fudge factor in *Fixed Costs. The fudges are multipliers, so if they are set to zero all categories will be zeroed out

2. are formulas still in clearinghouse/summation? May have been erased.

Solution

1. Use 1 as a fudge factor.

2. replace formulas (copy/paste from another estimate if necessary).

Comments

Entered 1/14/93 by Vinay.